Tenley Campus Construction Update: Sept. 14 - 18, 2015

Our Tenley Campus construction work is progressing well, and we are on schedule for classes to begin on January 11, 2016.

Here is a summary of the projects that our 1,100-person construction crew completed this week:

  • Installed the pavers between the Warren and Yuma buildings;
  • Put up high-density shelving on the second floor of the Pence Law Library;
  • Installed library offices and doors;
  • Finalized delivery and installation of the furniture;
  • Installed moveable classroom whiteboards.
Grading work begins, Aug. 17
Grading work begins, Aug. 17
Pavers installation work continues, Sept. 3
Pavers installation work continues, Sept. 3
Pavers installation completed, Sept. 17
Pavers installation completed, Sept. 17
Hallway outside Founders' Hall
Hallway outside Founders' Hall
100-Seat classroom in the Warren Building
100-Seat classroom in the Warren Building
Yuma Building
Yuma Building
Warren Building and the Courthouse
Warren Building and the Courthouse
Warren Building and the Pence Law Library
Warren Building and the Pence Law Library
Almost finished bathrooms
Almost finished bathrooms